City
Reykjavik, Iceland
Year of realisation
2005
Owner
Alcoa
Contract value
4 500 000 $
Engineer
Bechtel Overseas Corporation
Contractor
Bechtel Overseas Corporation
The energy from the smelter is recovered.
Main challenges
Construction phase completed in 3 months. In order to do so, pre-assembled components and building were designed.
Design-build building, thermal power plant, steam.
Services : Electricity, piping, ventilation.
Project number : 5009